This 4:1 concrete mix calculator converts a target concrete volume into the materials to batch it: cement (in 50 kg bags), sand and no coarse aggregate — it's a sand-cement mix, plus a water estimate at a 0.5 water-cement ratio.
كيفية استخدام هذه الحاسبة
- أدخل أبعادك — أقدام للأطوال، بوصات للسماكة.
- اضبط الخيارات — نسبة الهدر وحجم الكيس وسعر الخرسانة المحلي.
- اقرأ نتائجك — يتم تحديث الحجم والأكياس والوزن والتكلفة مباشرة أثناء الكتابة.
الصيغة
Dry volume = wet volume × 1.54, split in 4:1 proportions by volume مثال محلول: For 1 m³ of 4:1: dry volume 1.54 m³ ÷ 5 parts = 0.308 m³ cement (≈ 9 × 50 kg bags) and 1.232 m³ sand.
The 4:1 mix (4 parts sand to 1 part cement — mortar, render, screeds and repairs) is batched by volume: four sand to one cement with no coarse aggregate. The concrete calculator 4 1 mix is really a strong mortar/screed: bedding slabs, rendering walls, and repairs — not structural pours.
The 1.54 dry-volume factor matters: mixed concrete compacts, so you need about 54% more loose dry material than the finished volume. Skipping this factor is the classic under-order in hand batching.
Batch consistently — use the same bucket or gauge box for every part, keep the water-cement ratio near 0.5 (about 25 litres per 50 kg cement bag), and mix full bags of cement to avoid weighing errors.
الأسئلة الشائعة
أسئلة شائعة حول 4:1 concrete mix calculator.
What is a 4:1 concrete mix?
Parts by volume — 4 parts sand to 1 part cement — mortar, render, screeds and repairs. four sand to one cement with no coarse aggregate. The concrete calculator 4 1 mix is really a strong mortar/screed: bedding slabs, rendering walls, and repairs — not structural pours.
How strong is a 4:1 mix?
A 4:1 sand-cement mix reaches mortar-class strength (≈ 1,500 psi) — it's for bedding, render and repairs, not structural concrete.
How much water do I add?
Target a 0.5 water-cement ratio: about 25 litres per 50 kg bag of cement. Add most of the water first, then trim to a workable, not soupy, consistency.
Why multiply by 1.54?
Loose cement, sand and aggregate contain air voids that close up when mixed and compacted — 1 m³ of finished concrete consumes about 1.54 m³ of loose dry ingredients.